Streamlining and Improving Efficiencies in the RCRA Hazardous Waste Permitting Program; Notice of Virtual Public Meetings and Request for Information
[Federal Register Volume 91, Number 225 (Tuesday, November 24, 2026)]
[Notices]
[Pages 75852-75855]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2026-23882]
=======================================================================
-----------------------------------------------------------------------
ENVIRONMENTAL PROTECTION AGENCY
[EPA-HQ-OLEM-2026-9571; FRL-13652-01-OLEM]
Streamlining and Improving Efficiencies in the RCRA Hazardous
Waste Permitting Program; Notice of Virtual Public Meetings and Request
for Information
AGENCY: Environmental Protection Agency (EPA).
ACTION: Notice and request for information.
-----------------------------------------------------------------------
SUMMARY: This document announces and initiates an EPA effort to
streamline the Resource Conservation and Recovery Act (RCRA) permit
program and to remove associated barriers to redevelopment. This effort
will satisfy an Agency Priority Goal established by the EPA
Administrator to streamline the permitting process and improve
efficiencies to unleash economic growth. In this document, EPA seeks
information to help identify inefficiencies in the permit process and
ideas for streamlining, including ideas that would reduce the time,
uncertainty, and costs involved in issuing a permit. EPA also seeks
information to help identify situations where the RCRA permit presents
barriers to redevelopment of and/or parceling of RCRA treatment,
storage, and disposal facilities, and ideas to overcome those barriers.
EPA will consider information submitted as it develops a plan to
address the inefficiencies in, and barriers presented by, the current
RCRA permit program. This document also announces four virtual public
engagement sessions that will supplement the request for information by
providing individual participants an opportunity to provide oral
comments on these issues as well.
DATES: Comments must be received on or before January 25, 2027.
ADDRESSES: Any member of the public may send comments, identified by
Docket ID No. EPA-HQ-OLEM-2026-9571, by any of the following methods:
Federal eRulemaking Portal: https://www.regulations.gov
(our
[[Page 75853]]
preferred method). Follow the online instructions for submitting
comments.
Mail: U.S. Environmental Protection Agency, EPA Docket
Center, Office of Land and Emergency Management Docket, 1200
Pennsylvania Avenue NW, Washington, DC 20460.
Email: [email protected]. Include Docket ID No. EPA-HQ-
OLEM-2026-9571 in the subject line of the message.
Hand Delivery or Courier: EPA Docket Center, WJC West
Building, Room 3334, 1301 Constitution Avenue NW, Washington, DC. The
Docket Center's hours of operation are 8:30 a.m. to 4:30 p.m. EST,
Monday-Friday (except Federal Holidays).
Instructions: All submissions received must include the Docket ID
No. for this action.
Comments received may be posted without change to https://www.regulations.gov/, including any personal information provided. For
detailed instructions on sending comments and participating in the
virtual public engagement sessions, see the ``Public Participation''
heading of the SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: For further information on the
sections of this document addressing improvements to the permit
process, contact Nadja Solis Marcano, Waste and Chemical Implementation
Division, Office of Resource Conservation and Recovery, U.S.
Environmental Protection Agency, telephone number (202) 566-0356, email
address: [email protected]; or Lilybeth Colon, Waste and
Chemical Implementation Division, Office of Resource Conservation and
Recovery, telephone number (202) 566-0320, email address:
[email protected]. For information on the sections of this
document addressing barriers to redevelopment and parceling of RCRA
facilities, contact Barbara Foster, Waste and Chemical Implementation
Division, Office of Resource Conservation and Recovery, telephone
number (202) 566-0382, email address: [email protected].
To register for the virtual engagement sessions, please either
submit the online registration form available at EPA's Hazardous Waste
Permitting website at https://www.epa.gov/hwpermitting or contact Nadja
Solis Marcano at the contact information above. For information on
access or services for individuals with disabilities, or to request
accommodation of a disability, please contact Nadja Solis Marcano, at
the contact information above, at least ten (10) days prior to the
meeting to give the EPA as much time as possible to process your
request.
SUPPLEMENTARY INFORMATION:
I. Public Participation
The Agency requests public comment on issues described later in
this document. Public comment can be submitted to the docket for this
rulemaking as described in the Addresses section above. The Agency also
announces four public engagement sessions during which EPA will also
accept oral comments on the issues discussed in this document. The
public engagement sessions are intended to supplement the requests for
information in this document; participation in the public engagement
sessions is not required to submit public comment on the issues
discussed in this document. EPA will take notes to document comments
made at the public engagement sessions, which will be made available in
the docket, but the Agency strongly encourages speakers to submit their
presentations to the docket as well.
The dates and times of these public engagement session and
instructions for participating are available on the Hazardous Waste
Permitting Program's website at https://www.epa.gov/hwpermitting. For
purposes of organization, each of the virtual public engagement
sessions is targeted to an audience representing a sector of the
general public. Though participants are encouraged to attend their
targeted session, all sessions are open to the general public.
Advance registration is encouraged to secure a place on the agenda.
A general agenda listing pre-registered speakers in approximate order
will be available in the docket and on EPA's Hazardous Waste Permitting
website at https://www.epa.gov/hwpermitting the day before each
meeting.
II. Request for Comment
A. The Permit Process
The EPA Strategic Plan for FY 2026-2030 (Strategic Plan)
establishes as a priority goal to, by September 30, 2027, streamline
the permitting process and improve efficiencies so the Nation can
unleash economic growth while providing cost savings to hardworking
Americans. The Strategic Plan explains that by implementing cost-
effective regulations and streamlining permitting processes, the EPA
will demonstrate that protecting human health and the environment goes
hand-in-hand with economic prosperity, and that streamlining permitting
processes is a crucial step for facilitating investment and promoting
economic growth. The Strategic Plan further explains that the effort to
simplify regulations will remove redundancies and reduce delays, while
providing clear guidelines to aid businesses in navigating
requirements.
The Agency is issuing this document to obtain information from the
public that will support RCRA's implementation of the permitting effort
announced in the Strategic Plan. EPA is requesting comment in two
general areas--comment that will help identify inefficiencies and
redundancies in the current RCRA permit process, and comment that will
provide innovative solutions to overcome those inefficiencies and
redundancies.
EPA seeks comment on situations where the regulated community has
experienced inefficiencies, including unreasonable delays and/or
redundancies, in all areas of the permit process including but not
limited to:
Permit issuance and renewal--information required by the
application process, turnaround timeframes, process redundancies or
unnecessary processes.
Permit modification--determining the applicable class of
permit modification, information required, process redundancies or
unnecessary processes.
EPA seeks comment on ways to improve the efficiency of the permit
process including but not limited to:
Ways to modernize application and renewal procedures
through electronic tools.
Revisions to the permitting process, including the permit
modification processes, that might avoid redundancy and repetition.
Streamlined processes or information requirements that
could be implemented at particular phases of a facility's life (e.g.,
post-closure).
Ways to promote risk-based clean closure to eliminate the
need for post-closure permits.
B. Financial Assurance
A key goal of RCRA is to avoid the creation of Superfund sites, and
adequate financial assurance for closure, post-closure, third-party
liability, and corrective action is a vital component of the regulatory
scheme established to meet that goal. EPA is considering whether
revisions to the RCRA financial assurance program are necessary to
ensure that adequate and effective financial assurance mechanisms are
available at RCRA facilities.
EPA is requesting comment to identify situations where the current
RCRA Subtitle C financial assurance
[[Page 75854]]
program is outdated, inefficient, or ineffective including, but not
limited to:
Outdated aspects of the financial assurance mechanisms in
40 CFR part 264 subpart H and part 265, subpart H to reflect changes in
commercial practice, experience, and standards since the mechanisms
were promulgated.
Experiences related to unavailability of instruments or
instrument failure due to constraints imposed by the current
regulations.
How to best address situations and promote redevelopment
where there is no longer a viable owner or operator, and no financial
assurance is available.
EPA is also requesting comment on ways to improve the current
financial assurance program including but not limited to:
Ways that use of electronic financial assurance documents
and other electronic practices could improve the efficiency and
effectiveness of the financial assurance program.
Improvements that could be made to the financial assurance
regulations to overcome barriers to the availability and effectiveness
of the financial assurance instruments.
Improved methods to provide financial assurance for long-
term obligations such as post-closure care obligations (including those
that extend beyond the 30-year period) and corrective action
obligations.
Potential streamlining of the process for obtaining
instruments by expanding the scope of closure and post-closure
mechanisms to include corrective action costs.
C. Transferring Permit Obligations to Alternate Authorities
1. Background
RCRA section 3005(c)(3) requires that permits contain terms and
conditions as necessary to protect human health and the environment.
Section 3004(u) provides that, where corrective action is not completed
before permit issuance, permits issued to RCRA treatment, storage, and
disposal facilities must contain schedules of compliance for corrective
action for all releases of hazardous waste or hazardous constituents
from any solid waste management unit and assurances of financial
responsibility for completing such corrective action. RCRA section
3004(v) further requires that corrective action be taken beyond the
facility boundary as necessary to protect human health and the
environment.
Currently, EPA has implemented these statutory requirements by
requiring renewal of RCRA permits until the post-closure period is
complete,\1\ and until the obligation to address facility-wide
corrective action for releases of hazardous waste and hazardous
constituents from all solid waste management units at the facility is
satisfied.
---------------------------------------------------------------------------
\1\ See RCRA section 3004(u), 40 CFR part 264, and 40 CFR part
270. See also discussion of these authorities in the preamble of an
Advance Notice of Proposed Rulemaking entitled Corrective Action for
Releases From Solid Waste Management Units at Hazardous Waste
Management Facilities, 61 FR 19432@19463, May 1, 1996; and in a
memorandum from Barnes Johnson to the RCRA Division Directors,
December 15, 2016 entitled: Guidelines for Evaluating the Post-
Closure Care Period for Hazardous Waste Disposal Facilities under
Subtitle C of RCRA at page 13.
---------------------------------------------------------------------------
Increasingly, facilities are completing closure of their treatment,
storage, and disposal units, and these post-closure and/or corrective
action requirements are the only remaining permit obligations. EPA is
considering whether continuation of the permit throughout the post-
closure care period and until corrective action is complete is
necessary to meet the requirements of the statute or whether, and under
what conditions, the statutory requirements of section 3005(c)(3) and
sections 3004(u) and (v) could be met if post-closure and/or corrective
action requirements were transferred to an alternate state authority.
EPA has long recognized that state authorities such as enforcement
orders, if used as an alternative to RCRA corrective action
requirements for releases from solid waste management units, may impose
substantive cleanup requirements that are equivalent to those imposed
under a RCRA permit through RCRA corrective action authority. However,
EPA also recognizes that the existing RCRA permit systems in place that
provide for implementation and oversight of corrective action and post-
closure care provide procedural protections to help ensure
protectiveness.
2. Request for Comment on the Benefits of an Alternate Authority
Approach to Post-Closure Care and Corrective Action
EPA requests comment on the benefits of replacing RCRA permits with
alternate authorities to implement post-closure care and/or corrective
action obligations where the RCRA permit obligations present barriers
including but not limited to:
Examples of situations where the RCRA permit has been a
barrier to redevelopment of contaminated property.
Aspects of the permit or the permitting process that are
of particular concern in redevelopment scenarios.
Aspects of alternate authorities that make them preferable
to the RCRA permit to implement post-closure care and corrective action
for releases from solid waste management units.
3. Request for Comment on Alternate Approaches to Meeting the Statutory
Requirements
EPA is soliciting comment on how alternative authorities can
provide equivalent statutory corrective action and post-closure
requirements. EPA is also soliciting comment on how alternative
authorities can provide the protections currently afforded by the
permit process--that is, if post-closure and/or corrective action
permit conditions were transferred to an alternate authority, how the
standard to protect human health and the environment would continue to
be met until post-closure and/or corrective action is complete. EPA is
soliciting comment on how alternative authorities could replace the
protections currently provided by a permit including but not limited
to:
Reporting and notice--Procedural requirements that ensure
releases, corrective action needs, and possible post-closure extensions
are brought to the permitting authority's attention.
Continuity of responsibility--Transfer of permit
responsibilities to a new owner/operator, long-term responsibility for
post-closure care and corrective action obligations, and protections to
ensure these responsibilities remain enforceable during bankruptcy.
Accountability and inspection--Authority to make
enforceable comments on draft permits to ensure protective conditions
are included, as well as authority to inspect and enforce permit
conditions, including state-issued conditions.
Financial assurance--Requirements for financial assurance
for post-closure care and corrective action.
Public participation and transparency--Requirements for
public participation during permit issuance, modification, and renewal.
D. Parceling
The issue of transferring permit obligations to an alternate
authority also arises when an owner sells a portion of a RCRA permitted
facility. Owners and operators of RCRA facilities may seek to amend the
boundaries of the facility described in the RCRA permit to remove a
parcel being sold from the facility. Purchasers of property may be
hesitant to sign on to a RCRA permit and become jointly and severally
liable for facility-wide corrective action obligations and
[[Page 75855]]
seek to address remaining corrective action obligations through an
alternate authority. Regulators may be hesitant in parceling scenarios
to release owners and operators and property purchasers from RCRA
permit obligations because of concerns that doing so may allow them to
avoid corrective action obligations. Regulators further may be
concerned that selling parcels of a facility may deplete resources
available to address corrective action obligations on the remaining
facility.
These concerns may slow parceling decisions and hinder or even
prevent real estate transactions, including transactions that might
have provided for cleanup of facilities that might otherwise not be
addressed. EPA is seeking to develop parceling practices for RCRA
facilities that will provide guidelines for regulators enabling them to
make timely and informed parceling decisions that promote redevelopment
while ensuring that the goals of the statute are satisfied.
1. Benefits of Parceling
EPA requests comment on, and specific examples demonstrating, the
benefits of removing portions of facilities from RCRA permits upon
property transfer including but not limited to:
Situations where removing the RCRA permit requirement from
a facility parcel provided funds that otherwise would not have been
available to implement corrective action as necessary to protect human
health and the environment, including situations where the permittee
was no longer viable.
2. Barriers to Parceling
EPA requests comment to help identify and better understand any
barriers to parceling that may be created by the RCRA permit including
but not limited to:
Information explaining why the permit may be a barrier to
a property transaction.
Examples where the RCRA permit may have prevented or
slowed property transfer, particularly where the transfer of property
would have promoted cleanup.
3. Concerns Raised by Parceling Actions
EPA requests comment to help identify and better understand how
parceling of a RCRA permitted facility and releasing the owner/operator
and/or purchaser from permit obligations may impact whether the
statutory obligation to protect human health and the environment is
satisfied. EPA requests comment on regulators' experiences including
but not limited to examples where parceling transactions have created
incentives or hinderances for cleanup and redevelopment.
4. Overcoming Barriers to Parceling
EPA also requests comment on ways to overcome the barriers to
parceling RCRA facilities while ensuring that the statutory requirement
of RCRA for permit conditions necessary to protect human health and the
environment, and for corrective action permit conditions and financial
responsibility until corrective action is complete, discussed above,
are met. In particular, EPA solicits comment on:
Examples where a facility was parceled successfully and
the permit was retained, and how barriers were overcome in that
process.
Ways to support program implementers processing requests
for permit modifications associated with parceling transactions to
enable them to process those requests in a timely manner.
Practices or components of regulatory alternatives relied
on in parceling actions that regulators have found to effectively
assure that corrective action obligations at both the remaining RCRA
permitted facility and at the parcel will be addressed after the parcel
is sold and separated from the facility.
Financial mechanisms that program implementers can rely on
to finance future cleanup actions when RCRA financial assurance
requirements no longer apply.
E. Other Areas for Permitting Reform
Finally, EPA is soliciting comment on any other opportunities for
the Agency to improve the RCRA permitting program, streamline the RCRA
permitting process, and improve efficiencies so the Nation can unleash
economic growth while providing cost savings to hardworking Americans.
Because protecting human health and the environment goes hand-in-hand
with economic prosperity, the Agency requests input on ways to simplify
regulations, remove redundancies, and reduce delays, while providing
clear guidelines to aid businesses in navigating requirements and
maintaining protectiveness. EPA is generally soliciting comment on RCRA
permitting and specifically seeks ideas that would reduce the time,
uncertainty, and costs involved in issuing a permit and enable the
Agency to advance its strategic objective of achieving operational
efficiencies while upholding its mission to protect human health and
the environment.
III. Authority
EPA is authorized to implement the Hazardous Waste Permit Program
under the authority of sections 1006, 2002(a), 3002, 3003, 3004, 3005,
3010, 3013, and 7004 of the Solid Waste Disposal Act of 1970, as
amended by the Resource Conservation and Recovery Act of 1976, as
amended, by the Hazardous and Solid Waste Amendments of 1984 (HSWA), 42
U.S.C. 6905, 6912(a), 6922, 6923, 6924, 6925, 6930, 6934, and 6974.
These public laws combined are commonly referred to as the ``Resource
Conservation and Recovery Act'' (RCRA). EPA is soliciting comments and
announcing the virtual public engagement sessions to help inform future
policy actions under this RCRA authority.
Steven Cook,
Principal Deputy Assistant Administrator, Office of Land and Emergency
Management.
[FR Doc. 2026-23882 Filed 11-23-26; 8:45 am]
BILLING CODE 6560-50-P