Unlocking Heterogeneous Accelerator Flexibility in AI Data Centers: Sizing and Workload Allocation
Abstract
AI data centers are an emerging electricity demand, but limited local grid capacity could delay their connection and expansion.
While existing operational strategies consider spatio-temporal workload flexibility, few studies address the strategic sizing and allocation of diverse accelerator archetypes with different capital and energy-efficiency trade-offs.
This paper unlocks the flexibility potential of heterogeneous accelerators by jointly sizing and allocating different AI workloads (training, delay-tolerant batch work, and online inference requests) across sites and hours to meet the time-varying grid constraint at minimum cost.
Workload-specific throughput and energy coefficients link these decisions to facility power.
In a representative two-site case, heterogeneous sizing reduces daily cost by 6.5% relative to spatio-temporal scheduling with fixed capacity.
When evaluated using workload-specific performance, a capacity design based on workload-averaged hardware coefficients costs 7.7% more than the proposed design.
The proposed design also eliminates the envelope violations of an unconstrained design at a 0.25\% daily cost increase.
These results show how hardware heterogeneity and workload flexibility jointly shape economical, grid-compliant capacity plans.